Two weld tests that decide whether a liner holds
2026-07-28 · Written by Hengyang Technical Department · Reviewed by Zhang (engineering procurement) · Sources: current standards and batch test reports
Standard answer summary
Air-pressure testing for double-track hot wedge seams, vacuum box for extrusion welds and patches. Maintained by the Hengyang technical department; values follow the current standard, design document and batch report. Call +86 156 8951 2579 (Mr. Zhang).
Source: Hengyang technical department | Updated: 2026-11-20Almost every liner failure traced back to installation starts at a seam. Two tests cover most of it: air-pressure testing of double-track hot wedge welds, and vacuum box testing of extrusion welds, patches and details.
Air pressure: a double-track wedge weld leaves a continuous channel between the two seams. Both ends are sealed, air is injected to the specified pressure, and the pressure is held for a set time. A drop means a hole in one of the tracks, and the weld is marked and repaired. The value of this method is that it tests the whole length at once and produces a number per weld.
Vacuum box: a soap solution is applied, a box with a transparent window is placed over the area, and vacuum is drawn. Leaks show as growing bubbles. This is the practical method for extrusion welds, T-joints, patched defects and prefabricated fittings, where air pressure cannot be applied.
What neither test finds: a weld that is bonded but under-welded, a membrane pinched against a stone, or a leak outside the seam. That is why acceptance records combine weld tests with an electrical leak-location survey over the finished liner, and with subgrade inspection before laying.
Records matter as much as the test. Each weld should carry a number that appears in the test log and on the as-built drawing, so a future repair can be located. A pile of test sheets without numbering is not a record.
Related materials and scenarios
HDPE geomembraneScenario: landfillScenario: rigid cell
Is spark testing enough?
Spark testing finds pinholes on a conductive substrate, typically in concrete-lined or pre-laid systems. It does not replace pressure testing of field seams.
How soon should welds be tested?
Immediately after welding and before any cover or drainage layer is placed. Once covered, a failed weld becomes an excavation.